Mold Cavitation Calculator
Use this Calculator to find the No of Cavities requirement in mold based on Customer Requirements of Parts Quantity & Moulding Lead Time
Reduce the Moulding Lead time by few days and check Cavitation to met Customer Demands soon. For Example, To Produce 20000 Parts with 5 Days require 48 Cavity Mold. However, If the Moulding lead time reduced to 2 Days, then the mold requires 118 Cavity.
Quantity per Order – Quantity of Parts required per purchase order
Eg – 20000 Nos
Cycle Time (in Mins) – Moulding Cycle Time per Shot
Eg – 6 mins
Working Time (per day in mins) – Working Time per day
Eg – 510 mins
Moulding Lead Time (in days) – Lead Time of Moulding Process per order
Eg – 5 Days (Needs to Complete 20000 nos production with 5 Days)
No of Cavity Required in Mould – 48 Cavities